Get a Quote

Let's build your project together.

Request a quote for steel construction, welding and fabrication; our expert team will get back to you shortly.

Get a Quote →0352 322 11 19
Mehmet Yücel Yapı Çelik

Building a facility means hoping for tomorrow. We construct structures that meet the needs of industry leaders with modern, internationally standardized practices.

Company

  • About Us
  • Certificates
  • Our Machines
  • Factory Gallery
  • References

Services

  • Steel Construction
  • Welding & Fabrication
  • Steel Roofing
  • Plasma & Laser Cutting
  • Mezzanine Floors
  • Custom Projects
  • Steel Chimneys
  • Silos
  • Multi-Storey Steel Buildings

Explore

  • Projects
  • Blog
  • Contact

Write to us

Örenşehir Mah. Bayrak Cad. No:128, 38560 İncesu / Kayseri, Türkiye

0352 322 11 19

0532 794 05 40

info@mehmetyucelyapicelik.com.tr

Mon - Sat: 08:00 - 18:00

© 2026 Mehmet Yücel Yapı Çelik Sanayi ve Ticaret Limited Şirketi. All rights reserved.Personal Data Privacy Notice

Design & developmentCNZ Adworks
ISO 9001:2015ISO 14001:2015ISO 45001:2018EN 1090-2 EXC3ISO 3834-2:2021
Skip to content
Mehmet Yücel Yapı Çelik
Home
Company▾
Services▾
Projects
References
Blog
Contact
TR0352 322 11 19Get a Quote
  1. Home/
  2. Our Projects/
  3. Hasçelik Kablo

Hasçelik Kablo

Hasçelik Kablo
Hasçelik Kablo

As Mehmet Yücel Steel Construction, we carried out a steel truss structure with 28-meter spans and a total of 500 tons of steel construction for the Hasçelik Kablo facility. Starting in September 2021, the project was completed in November 2022 through a two-phase erection plan.

Two-Phase Erection Strategy

We divided the project into two stages to avoid disrupting Hasçelik Kablo's ongoing production operations. In the first phase, we completed the fabrication and erection of the 250-ton section by December 2021. Hasçelik Kablo put this section into service and began increasing production capacity. We moved to the second phase in September 2022 and completed the remaining 250-ton portion by November 2022.

Technical Specifications

The 28-meter clear-span steel trusses provided the wide, unobstructed working space required by the cable production line. All components—including main trusses, column-beam connections, and roof purlins—were fabricated at our Kayseri production facility. During erection, we employed precision measurement and application techniques in sections requiring integration with existing structures.

Throughout the 14-month project duration, we worked in coordination with Hasçelik Kablo, minimizing impact on production and delivering on schedule.

Project Details

Client
Hasçelik Kablo
Tonnage
500 Ton
Start
Eylül 2021
End
Kasım 2022