As Mehmet Yücel Steel Construction, we carried out a steel truss structure with 28-meter spans and a total of 500 tons of steel construction for the Hasçelik Kablo facility. Starting in September 2021, the project was completed in November 2022 through a two-phase erection plan.
We divided the project into two stages to avoid disrupting Hasçelik Kablo's ongoing production operations. In the first phase, we completed the fabrication and erection of the 250-ton section by December 2021. Hasçelik Kablo put this section into service and began increasing production capacity. We moved to the second phase in September 2022 and completed the remaining 250-ton portion by November 2022.
The 28-meter clear-span steel trusses provided the wide, unobstructed working space required by the cable production line. All components—including main trusses, column-beam connections, and roof purlins—were fabricated at our Kayseri production facility. During erection, we employed precision measurement and application techniques in sections requiring integration with existing structures.
Throughout the 14-month project duration, we worked in coordination with Hasçelik Kablo, minimizing impact on production and delivering on schedule.
Next
Innova Eva →